Use two independent estimates
- ✓Line-based: number of lines for your product × realistic daily output per line × working days
- ✓Output-based: the factory's daily output records over the last 10 working days × working days per month
Cross-check the inputs
- ✓Machines counted by type against the list
- ✓Workers present by department against the claim
- ✓Attendance register for the visit day
- ✓Current orders already using the lines
Capacity claim looks too good?
We count machines and workers and check output records.
Plan on the realistic figure
If the estimates agree with each other but not with the claim, plan delivery on the lower number and ask for a written production schedule.